Minutes of the LArg Front-end Optical Links Meeting
CERN
10th December 1997
Present :
Marie-Laure Andrieux ISN
Alexandre Chekhtman Novosibirsk
Jacques Colas LAPP
Bernard Dinkespiler CPPM
Olivier Martin CPPM
Robert McLaren CERN
John Parsons Nevis
Mark Pearce KTH
Erik Van der Bij CERN (part-time)
SUMMARY
~~~~~~~
(1) Status of the ANALOGUE link project
CPPM - O.Martin
Olivier reported that preliminary tests of the
`n-up' Sandia VCSEL arrays indicated good stability
and efficiency. Two of these VCSEL's would be placed
into the ISN `demonstrator' packaging (see below).
Results from these devices would form the basis of
a final paper on the analogue optical link development.
Olivier also remarked that he had been in contact with
K.Lear at Micro-optical regarding commercial costs for
VCSEL arrays developed by Sandia. If a new mask had
to be built for the long-lead (approx 1 mm.) versions
that we use, the prices (for a quantity of 2000) would
be $100's per array ! The short-lead (approx 100 um)
versions, however, are in stock but no price was quoted.
The question of whether we can arrange for the Sandia mask
to find its way to Micro-optical was raised - as we have,
in principle, paid for it's development. Olivier agreed to
look into this.
ISN - M-L.Andrieux
Marie-Laure reported that the two `best-candidate' VCSEL
arrays would be incorporated into ISN demonstrators. Both
CPPM and KTH would receive one for final measurements.
The status of the Amphenol connector was also reported on.
Marie-Laure said that the mechanical tests on the ceramic had
been completed and that electrical tests would be completed
in January. By the end of January, optical and, in particular,
alignment tests would be started. Amphenol plans to have a
complete link prototype ready by the start of March.
KTH - M.Pearce
Mark reported on some measurements performed with Jesper
Söderqvist on a Sandia VCSEL array passively coupled to a
MT-connector. This followed the procedure successfully
used for the PIN-array in the receiver box. There were
some problems bonding the VCSEL array as the metalisation
came off the chip - only 6 from 16 channels were successfully
bonded.
The preliminary measurements with this passively aligned
VCSEL were encouraging. Final results on dynamic range
etc. will have to wait for the final ISN demonstrator
but Jesper noted that at present the link's dynamic range
was limited by noise (1mW/2uW=500 or <9 bits). Since there
is a cover-glass over the VCSEL, this noise maybe reflection
induced - this needs to be investigated. In summary,
passive alignment was shown to be possible even though
the ceramic used was optimised for PIN-arrays which have
a larger active area.
Finally, Mark said that the KTH receiver box would soon be
tested with fast transimpedence amplifiers at GHz speeds,
if possible.
(1) Status of the DIGITAL link project
Preliminary Results from October SARA Irradiations - M.Pearce
Mark presented preliminary results prepared with
Johan Lundquist on the neutron irradiation of commercial
VCSEL's from Honeywell (9 off) and Mitel (9 off). Both were
housed in ST-style capsules. Through-out the irradiation, the
VCSEL's were biased above threshold. During the irradiation,
P-I curves were taken for each VCSEL at regular intervals.
Mark presented plots showing that the VCSEL threshold currents
did not move significantly during the irradiation. He also
showed that, on average, the VCSEL light output at a given
current dropped by approximately 10%. The VCSEL's were biased
above threshold after the neutron beam was stopped. Annealing
behaviour was observed and the pre-irradiation light output
was recovered. The VCSEL's received an estimated total fluence
of approximately 1.7x10^13 n(1MeV)/cm^2.
Mark also reported on the irradiation of Hewlett-Packard ECL
G-link serialisers prepared by Bernard Dinkespiler. During
irradiation, only the PLL (analogue) part of the chip was
exercised. No loss of PLL functionality was observed during
the test. Back in the lab, Bernard tested the integrity of the
chips's data-way up to speeds of 200 MHz - no problems were
observed and the PLL worked with output frequencies up to
1.6GHz. The chips received an estimated total fluence of
approximately 0.8x10^13 n(1MeV)/cm^2. It should be noted that
since there was no data-flow through the chips, it was not
possible to check for SEU or SEL etc.
Finally, some results from the irradiation of commercial 8-way
multimode fibre-ribbon were shown. The ribbon was supplied
by ACOME and a 10m long section was irradiated. Initial
results indicated an attenuation of between 20-30% due to the
irradiation. There was some recovery after the irradiation was
finished, and the exact nature of this was still being studied.
The fibres received an estimated total fluence of
approximately 0.5x10^13 n(1MeV)/cm^2.
In all cases, more sophisticated tests are planned in the
future. For example, with Gb data flows through components
and BER tests etc.
News from Co-ordination Meetings - M.Pearce
Mark reported on the advent of an overall ATLAS co-ordination
working group for front-end links. Full details can be found
from : http://www.cern.ch/Atlas/GROUPS/FRONTEND/links/
In particular, Mark pointed out that the working group has
requested workplans to help assess commonality between
subdetectors and that the electronics co-ordinators had
requested some uniformity for link costs within CORE.
Timescale and Milestones - M.Pearce
In the spirit of the ATLAS links working group, Mark presented
a preliminary draft of a workplan and associated milestones
for LArg links in the coming 18 months. Mark expressed a desire
to develop this into a more formal document in the New Year,
to be presented to the LArg community as a whole. To set the
scene, he indicated the following milestones :
o Freezing of front-end system (data-flow) architecture
(see talk by John Parsons)
o Choice of link architecture. Parallel or serial.
EMC considerations between preamps and serialiser
clocks.
o Definition of a neutron, gamma, other (?) irradiation
programme
o Definition of a demonstrator link programme
He also discussed the need for some planning of accelerated
aging tests and interface to installation engineers (see talk
by Mark later).
In order to meet these milestones, Mark thought that given
the geographical separation of the groups involved it would
be sensible to define distinct projects.
A list of possible project areas was presented based around the
need to be able to perform realistic function tests during
irradiation and aging tests, for example. These projects would
be refined in time for the next meeting.
Proposed Link Baselines - B.Dinkespiler
Bernard presented plans for Gb demonstrator links and test-beds.
A serial version used HP G-link Gb serialisers with
inter-changeable optics, such as : ST-housed VCSEL's + drivers
or commercial transceiver modules. The PCB's for this project
were expected to be received back from industry very soon.
Bernard also presented an idea for a pseudo-random BERT based
on a pattern generator and a FIFO-buffered Altera-based error
detector (see the transparencies for a clearer picture !).
A parallel version using, in the first instance,
an Optobus as the optical elements is also being
designed. In this version, there are 4 data lines and
one clock line at 320 MHz to strobe the data out.
Bernard said that these set-ups could be adopted for EMC (using
the test-beam electronics with no beam) and irradiation tests.
Radiation Testing Issues - M-L.Andrieux
Marie-Laure presented details of the SARA time schedule for
1998. Since SARA closes at the end of July 1998 it is
essential to fully use this facility next year. A preliminary
testing schedule was shown and will be refined over the
coming months. She also explained that post-SARA neutron
irradiations may be possible at Orleans.
A Gamma Irradiation Facility in Stockholm - M.Pearce
Mark reported that Johan and he had visited a hospital in
Stockholm which had a Co-60 gamma source. Dose rates of 2.1 Gy
per minute were possible @ 60cm from the source. The beam area
at this distance is approximately 20cm x 20cm. The source
was only accessible at the weekend and during a typical 70 hour
period, a total dose of 8820 Gy was possible, which is
perfect for LArg testing needs. Mark and Johan would carry
out tests, like those reported on earlier in the meeting
at SARA, in January to gain experience with this new facility.
Comments on LAr Link Architecture - J.Parsons
John reported that the baseline architecture for detector
control and TTC distribution has :
o one control card per half front-end crate for
fanning-out and distributing clock (point to point),
TTC and control (bussed) to each front-end board
(FEB).
o a single link for bringing TTC information to each
control card (from TTC system)
o a single link bring control words (from the ROD)
John pointed out that this scheme has many single point
failure modes which could lead to the loss of half a
front-end crate (1792 calorimeter channels). He noted that it
would perhaps be better to bring separate links per FEB, ie:
one link for TTC and another for serial control. This could be
done optically, or with copper as the data speeds are rather
modest (approximately 5 Mb/s for control and 200 Mb/s for TTC).
For FEB-ROD links, there are 128 calorimeter channels per FEB
each running at a nominal 1.28 Gb/s. Each FEB serves a single
depth segment (ie: PS, strips, middle or back). However, the
L2/DAQ requires that trigger towers (SUMMED over PS, strips,
middle back) are available in a single ROD. A remapping of
calorimeter channels onto trigger towers between FEB and ROD
could be achieved by re-grouping into sets of 32 channels,
rather than 128. In fact, the FEB architecture is designed such
that a 32 bit word is composed of 16 two bit contributions from
separate ADC's (each ADC serves 8 calorimeter channels). So,
one could naturally achieve the re-mapping using 4 links per
FEB (8 for the presampler). This also means that only 32
calorimeter channels would be lost if a single link went down.
Of course, the cost of such links is a major concern when
considering such a strategy, given the extra number of links.
After this presentation there was some discussion. In particular
it was noted that the TTC/control and FEB-ROD links could
effectively be decoupled as the responsibilities lie with
different people, ie: the the TTC/control links are the
responsibility of the trigger/DAQ group. This means that the
FEB-ROD links remain unidirectional with only the
emitters in a high radiation environment.
Installation Issues - M.Pearce
Mark reported on a meeting with Mark Hatch regarding the
installation of LArg FE-link optical fibres. Mark H. said
that the installation team would like to have fibre routing
drawings completed for the installation TDR in September 1998.
Several points, in particular, were discussed :
o In the TDR it is assummed that a single fibre will
be run from FEB to ROD. Due to the high radiation
environment in the crack region, this may not be
possible. If a special radiation hard fibre were to
be used in the crack then a patch panel would be
needed somewhere to allow connection to a more
standard `off the shelf' (cheaper !) fibre. The
position of this patch panel needs to be accounted
for in an already congested part of the detector.
o Mark H. had suggested that if many FEB's were routed
into individual fibres housed in a ribbon then it
may be sensible to have the option of replacing
fibres in case they are broken during access periods.
o In order to allow designers to proceed with the
allocation of space for fibres, a worse case scenario
was presented. Assuming there are 30 FEB's per crate,
each with a maximum of 4 data connections and 2
TTC/control connections, implies a total of 180
fibres per front-end crate. These fibres could be
supplied in ruggedised ribbon-cables.
There was some discussion after this presentation : Where a
patch panel for fibre type conversion is needed, then there is
the possibility of doing the trigger tower `remapping' here.
The additional size needed for the patch panel would need to
be evaluated though. Jacques asked if in the case where the
ROD is placed in the control room, 200m from the detector,
whether continuous fibres could be over the full distance
or whether an extra patch is needed. He also asked what the
minimum length a fibre can be when fanning out signals from a
central point to avoid reflection problems and ensure mode
mixing.
TRANSPARENCIES
~~~~~~~~~~~~~~
Copies of transparencies will be sent to :
o A representative from each of the participating
groups (CPPM, ISN, KTH, SMU)
o The ATLAS secretariat
M. Pearce
(December 16th 1997)
M.P.