9.00 - Results, status ( with Milestone review ) and plans
for Analysis+Simulation.
Formation of a simulation team:
Modeler architects subgroup
Modeler simulation run and analysis-tools subgroup
Model-analysis group
Requirements for Models to be simulated
Plan for reaching the level required for
simulating models to meet MONARC milestones
Requirements of analysis models, in order
to be able to characterize which are -- and are
not -- feasible.
Criteria for the "Choice of the models to be
to be simulated".
Plan to demonstrate convincingly that there
exist Models matching the foreseen resources,
and supporting a sufficient body of LHC "analysis"
in total. [Or alternatively: that additional
resources may be required in some areas.]
9:00 Iosif Legrand "Status of the simulation program"
demonstration (if possible from 40-SD-01)
15.45 - Workplan for Phase2
Draft Workplan for July-December, with review of the steps of
Phase1C and Phase2 (Chapter3 of PEP and elsewhere in PEP)
WG coordinators 15' minutes each one
16.45 BREAK for 15 minutes
17.00 Ideas for Phase3
- Framework, issues to be adressed in phase3 and its time span,
attitudes in ATLAS, CMS, LHCb; actions to be taken
L.P., H.N., F.Harris + Discussion
18.00 - Sharing of the work and schedule for writing the Progress eport
(to be ready by June 9th)> H.N/L.P., Coordinators