Capillary Production
Intro
Here you will find the capillary production data for the Pixel Detector. Schedule, QA Process, Production Progress, Travelers, etc.
Numbers Required
Barrel
Layer 2
- Nominal Length: 110cm
- Number Regular Fitting: 22
- Number Short Fitting: 4
- Spares Regular: 2
- Spares Short: 1
Layers 0/1
- Nominal Length: TBD
- Number Regular Fitting: 20
- Number Short Fitting: 10
- Spares Regular: 2
- Spares Short: 1
Disk
Disks 1,2,3
- Nominal Length:
- Number: 24
- Spares: 0
Opto
- Nominal Length: 120cm
- Number: 8
- Spares: 1
Schedule
Following is the planned production schedule for barrel capillary production. As of this time, disk capillary production has been completed.
Barrel
At the moment, only layer 2 schedule is shown.
https://twiki.cern.ch/twiki/bin/viewfile/Main/CapillaryProduction?rev=1;filename=BarrelCapSchedule-6Sep06.xls
Production Progress
Barrel
The production tracking spreadsheet is updated frequently and may be found
here.
Representative weights of the capillaries are
here. Not all capillaries will be weighed. Uniformity is good enough to not need this.
Disk
Capillaries for both endcaps have been completed. 24 (12 per endcap) good capillaries were produced with no spares (spares will be produced on demand if a failure occurs later in the integration). The production tracking spreadsheet may also be found
here. The weights are
here.
Repairs
The items linked in this section describe repair procedures for the capillaries.
Development of a splice repair for a disk capillary may be found in the folder
here.
--
NealHartman - 06 Sep 2006