____________________________________________________________________________ A NEW DRAFT MODULES PROGRAMME: THROUGH TO AUGUST 2000 [1st June 1998] _____________________________________________________ [A] Milestones _____________________________________________________________________________ [update: 26.7.98] PROVISIONAL DRAFT FOR DISCUSSION of REVISED MODULES PROGRAMME _____________________________________________________________ - Module-2 = prototypes; another iteration anticipated - Module-1 = final components, but not from production batch - Module-0 = final components from production order Modules (Barrel & Forward) : Proposed/ GT's V5 - Barrel module design frozen Oct 98 - TPG, Beryllia delivered - (b) Module-2 assembled and measured - (b) Module-2 irradiated - (b) Multi-module test - (b) Module-2 fully evaluated Mar 99 _________________________________________________ - Forward module design frozen Oct 98 - TPG, Beryllia delivered - (f) Module-2 assembled and measured - (f) Module-2 irradiated - (f) Multi-module test - (f) Module-2 fully evaluated Mar 99 __________________________________________________ - Barrel & Forward Design review Apr 99 ______________________________________________________ - Assembly tooling review Apr 99 - Test and QA procedure review Apr 99 - (b) Module-1 assembled Apr 99 - (b) Module-1 measured (geometry, thermal, electrical) - (b) Module-1 irradiated Jun 99 - (b) Module-1 measured (geometry, thermal, electrical) Aug 99 - (b) Multi-module test - (b) Module-1 fully evaluated Aug 99 _________________________________________________ - (f) Module-1 assembled Apr 99 - (f) Module-1 measured (geometry, thermal, electrical) - (f) Module-1 irradiated Jun 99 - (f) Module-1 measured (geometry, thermal, electrical) Aug 99 - (f) Multi-module test - (f) Module-1 fully evaluated Aug 99 _________________________________________________ - Module Design Review Sep 99 Aug 99 _____________________________________________________ - Specification for procurement Sep 99 - PRR Oct 99 Sep 99 _____________________________________________________ - Call for tender Oct 99 - Contract placed Nov 99 - Module0 ready for tests Jan 00 Apr 00 - Module0 irradiated May 00 - Multi-module test - Module0 tests complete Mar 00 Sep 00 ____________________________________________________ - Module assembly QA & test procedure complete Mar 00 - Module assembly tooling available Mar 00 - Start of module production Apr 00 Sep 00 - 10% of module production Aug 00 Mar 01 (SYSTEMS TESTS) ____________________________________________________ - 25% of module production Dec 00 Sep 01 - Module production complete Aug 02 Sep 02 _____________________________________________________ Note: G.Tappern's SCT Master Schedule is available from the ATLAS EDMS web page, http://edms.cern.ch/atlas/ (-> ATLAS -> ID -> SCT), or a copy on the SCT module page. [B] ELECTRICAL MODULES THROUGH TO 10% PRODUCTION The general target numbers for module production are for discussion at the June 1998 SCT Week: _____________________________________________________________________________ MODULE TYPE: | | | 10% || | | | 10% | | B-2 | B-1 | B0 |Prodcn|| F-2 | F-1 | F0 |Prodcn| _______________________________________________________________________| | 1998 | 1999 | 1999 | 2000 || 1998 | 1999 | 1999 | 2000 | ________________________________________________________________________ |May to|Sep to|Mar to|Oct to|May to||May to|Sep to|Mar to|Oct to|May to| |nd Aug|nd Dec| June |nd Dec|August||nd Aug|nd Dec| June |nd Dec|August| _____________________________________________________________________________ Japan | 1 | 3 | 5 | 8 | 50 || | | | | | ______|______|______|______|______|______||______|______|______|______|______| USA | 1 | 2 | 4 | 6 | 50 || | | | | | ______|______|______|______|______|______||______|______|______|______|______| Scdvan| 1 | 2 | 4 | 6 | 50 || | | | | | ______|______|______|______|______|______||______|______|______|______|______| UK-B | 1 | 3 | 5 | 8 | 50 || | | | | | ______|______|______|______|______|______||______|______|______|______|______| Cen-EU| | | | | || 1 | 2 | 4 | 8 | 60 | ______|______|______|______|______|______||______|______|______|______|______| CERN/ | 1 | | | | || 1 | 2 | 3 | 6 | 60 | _G/A__|______|______|______|______|______||______|______|______|______|______| UK-V | | | | | || 1 | 2 | 4 | 8 | 60 | ______|______|______|______|______|______||______|______|______|______|______| TOTALS| 5 | 10 | 18 | 28 | 200 || 3 | 6 | 11 | 22 | 180 | _____________________________________________________________________________ Approximate Detector needs: | 25 | 50 | 90 | 120 | 800 || 20 | 30 | 50 | 120 | 800 | _______________________________________________________________________________ For detector orders [for ELECTRICAL MODULE production alone] this implies the following timescales for purchases (with 50% spares/relevant studies, and 6 months of fabrication), and also imply order for [working] FE chip sets on the same timescales: Module-2 Module-1 Module-0 10% prod. Order by May 1998 Oct 1998 June 1999 Nov 1999 __________________________________________________________________________ Barrel: 75 135 180 1200 Forward: 45 75 180 1200 FE chips: 300 600 900 7000 __________________________________________________________________________