10:00~: N-Lab Meeting (could not participate because of the high rate test)
High rate test
9:00~: start to establish the same environment as yesterday.
ROD configuration failed because of IS server problem
could not update information after disable SSW8 (Inner) from FE link 9 on ROD on the TGC parameters panel.
discussed with Daniel and fixed by removing the repository (e.g. tgc.TgcRunParameters_RodC11) by hand from IS monitor panel.
C02 could not be configured because one JRC route for PSB (0x02830003) SLB0/1 could not taken in 10 times. --> run with C03, 05, 06, 07, 08, 09, 11, 12
SFI complained again because of the inconsistency of BCID between TGC ROD and CTP ROD.
the inconsistency was happened when we change L1 prescale key on the fly from 10kHz to 50kHz --> need to discuss with Thilo and Lorne.
SEU on C05
When the SEU was detected on ROD status panel, non-zero values were observed by using JtagAccess command. --> Disabled from global. (Before disabling the sector, we should shoot the PsReset and check the behavior...)
BCR delay on TTCvi
In the oks xml file for tdaq-01-09-01, it was defined as 125.
But the latest one is defined as 25. --> difference is 100. (consistent with the report of SFI yesterday)
I don't know who changes, but I'll change it to the original value (125) and the offset on ROD (3563). --> not yet.
15:00~: run with 50kHz except for C05
17:00~: test new ROD firmware (don't know the detail)
TGC Online SW
Configuration SW
Migration to tdaq-02-00-02
Compile
OK (except for ROD, Gnam package)
OKS xml
OK
State Transition
OK (TTC and FE, No HW Access mode)
Drivers
Not yet (ask TDAQ people after compiling all packages)
Migration to SLC5
Not yet.
Start to discuss with the muon online sw experts.
Bug
Some values are reported as ERROR even though the read back value is equaled to the reference value (tdo = tdi).
Configuration Database
Check out parameters from Oracle with the latest API --> OK
Some bugs/modifications are requested to Daniel. --> mainly inconsistency between Text and Oracle.
Download parameters to real ASICs/FPGAs using TDAQ IGUI --> OK
Elapsed time to download parameters from DB
Text
~1.2 sec/sector
Oracle
~ 8.4 sec/sector
~25 sec/segment --> ~150sec in total to configure
Physics
Daily discussion:
No discussion today...
My interests
No study today...
Today's HEP arxiv
All-Order Corrections To Higgs Boson Production In Association With Jets arXiv:0906.1965